Commercial Projects

Brookfield Place

Brookfield-Place_big

Contract: To supply four York centrifugal chillers with varying duties so that they can be staged to suit the building demand, giving light load to total cooling load with standby capacity.

Client:

Brookfield Multiplex

Mechanical Contractor:

Triple M

Location of the Project:

St Georges Terrace Perth

Consultant:

Design & Constructed by Triple M

Project Requirements:

To supply four York centrifugal chillers with varying duties so that they can be staged to suit the building demand, giving light load to total cooling load with standby capacity.

Cooling Load:

Total cooling 9,300 kW

Details of the Chiller Set:

Supply of:
2 x 3,500 kW YK centrifugal
1 x 1,300 kW VSD YK centrifugal
1 x 1,000 kW VSD YK centifugal chiller

Chiller Set Supplied in:

September 2009